Journal of Engineering, Project, and Production Management, 2021, 11(2), 158-168

 

Optimization of Earthmoving Operations Planning: A Novel Approach Considering Interferences

 

Roberto X. de Lima1, Ernesto F. Nobre Júnior2, and Pedro G. P. S. Fernandes3

1PhD Candidate, Dept. of Transportation Engineering, Federal University of Ceará, 60020-181, Fortaleza, Ceará, Brazil, E-mail: rxdelima@yahoo.com.br
2Senior Lecturer, Dept. of Transportation Engineering, Federal University of Ceará, 60020-181, Fortaleza, Ceará, Brazil, E-mail: nobre@ufc.br
3MSc Student, Dept. of Transportation Engineering, Federal University of Ceará, 60020-181, Fortaleza, Ceará, Brazil, E-mail: pedrofernandes@det.ufc.br (corresponding author).

 

Project and Production Management

 

Received July 7, 2020; revised September 9, 2020; accepted September 19, 2020

 

Available online October 5, 2020

 

Abstract: The purpose of this paper is to present an optimization model for planning the distribution of materials in earthmoving operations, considering possible interferences between cut-and-fill sections such as rivers, vegetation, topographical features, or expropriations. The earth allocation problem incorporating interferences was modeled as a linear programming problem, aiming to minimize the total earthmoving cost while considering the constraints related to volume balance, construction project duration, and time for the release of traffic. The proposed linear programming model was run by an integrated system, using Excel for data analysis and IBM CPLEX as the optimizer. The mathematical model was evaluated by a sensitivity analysis and validated by a real-world project of a dam access road in the state of Ceará, Brazil. The unit costs and productivity rates used in the fictional example and in the real-world application followed the referential cost system created by Ceará’s Secretariat of Infrastructure (SEINFRA-CE). The proposed optimization model achieved reasonable processing times for all tested applications, presenting itself as a viable and efficient option for planning earthmoving operations. Furthermore, the linear programming approach provided a 2.12% cost reduction for the real-world case study, when comparing the optimized solution and original budget. This study explored the problem of earth allocation with interferences using a linear programming approach, while avoiding complex modeling issues found in recent literature. As a result, this paper proposes a user-friendly optimization system that can be easily utilized by construction companies and departments.

 

Keywords: Highway engineering, earthworks, optimization, mathematical programming.

Copyright © Journal of Engineering, Project, and Production Management (EPPM-Journal).

This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivs 4.0 Unported License.

Requests for reprints and permissions at eppm.journal@gmail.com.

Citation: Lima, R. X. D., Nobre, E. F., and Fernandes, P. G. P. S. (2021). Optimization of Earthmoving Operations Planning: A Novel Approach Considering Interferences. Journal of Engineering, Project, and Production Management, 11(2), 158-168.

DOI: 10.2478/jeppm-2021-0016