Journal of Engineering, Project, and Production Management, 2011, 1(1), 3-12 A Simulation Model for Spatial Scheduling of Dynamic Block Assembly in Shipbuilding
Zhuo Liu1, David K. H. Chua2, and Keng Hwee Wee3 1Postdoctoral Research Fellow, Department of Civil Engineering, National University of Singapore, Singapore, E-mail: cveliuz@nus.edu.sg (corresponding author). 2Associate Professor, Department of Civil Engineering, National University of Singapore, Singapore, E-mail: cvedavid@nus.edu.sg 3Senior Vice President, Singapore Sembcorp Marine Ltd, E-mail: khwee@sembcorpmarine.com.sg
Engineering and Production Management
Best Paper of EPPM 2010 Conference
Received May 9, 2011; received revision June 2, 2011; accepted June 4, 2011
Available online June 28, 2011
Abstract: Accurately predicting the required spatial resource for aggregate block assembly in shipyard production is difficult due to the following reasons: 1) lack of optimal block on-jig configuration and 2) the dynamic and stochastic nature of production system. Consequently, managerial objectives are seldom achieved without effective production planning and control. In this study, a look-ahead scheduling mechanism with an application of discrete-event simulation is proposed to solve the dynamic spatial scheduling problem. A systematic simulation-based framework is suggested for validating schedules generated at high-level planning together with a heuristic-based optimizer for improving spatial resource utilization. Through imitation of the dynamic spatial operation under various priority rules, statistical analysis of resultant performance can be conducted to select the best performing control policy. A case study with computational experiments is performed and results are reported. Issues relevant to system implementation are highlighted as well.
Keywords: Discrete-event simulation, block assembly, shipbuilding, dispatching rule, spatial scheduling. Copyright © Journal of Engineering, Project, and Production Management (EPPM-Journal). This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivs 4.0 Unported License. Requests for reprints and permissions at eppm.journal@gmail.com. Citation: Liu, Z., Chua, D. K.H., and Keng, H. W. (2011). A Simulation Model for Spatial Scheduling of Dynamic Block Assembly in Shipbuilding. Journal of Engineering, Project, and Production Management, 1(1), 3-12. DOI: 10.32738/JEPPM.201107.0002
DOI:
10.32738/JEPPM.201107.0002
|